05:15:00 |
Countdown Clock Initialization |
HOLDING |
Countdown Initiation |
HOLDING |
Countdown Briefing |
05:00:00 |
Redundant Inertial Flight Control Assembly Activation |
04:50:00 |
Launch Area Clear |
04:35:00 |
Go/No GO for Propellant Loading |
04:30:00 |
Cryogenic Tanking begins |
04:30:00 |
Common Booster Core LH2 Tank Chilldown |
04:10:00 |
Common Booster Core LH2 Loading in Slow Fill |
04:00:00 |
CBC LH2 Load Transitions to Fast Fill |
04:00:00 |
Common Booster Core LOX Tank Chilldown |
03:50:00 |
Common Booster Core LOX Loading in Slow Fill |
03:45:00 |
CBC LOX Load Transition to Fast Fill |
03:35:00 |
C-Band Beacon Checkouts, GPS Verifications |
03:25:00 |
Delta Cryogenic Upper Stage LH2 Tank Chilldown |
03:25:00 |
Guidance System Activation |
03:10:00 |
CBC LH2 Topping – Fill & Drain Valve Checks |
03:05:00 |
DCSS LH2 Loading |
02:55:00 |
CBC LOX Topping – Fill & Drain Valve Checks |
02:45:00 |
Delta Cryogenic Upper Stage LOX Tank Chilldown |
02:45:00 |
Launch Weather Briefing |
02:35:00 |
DCSS LOX Loading |
02:00:00 |
DCSS LH2 Topping |
01:35:00 |
DCSS LOX Topping |
01:25:00 |
Radio/Telemetry Link Checks, FTS Checks |
01:10:00 |
Command Receiver Decoder Testing |
01:00:00 |
Flight Termination System Testing complete |
00:50:00 |
RS-68 Engine Spin Start Pressurization |
00:50:00 |
RS-68 Gimbal Steering Checks |
00:25:00 |
Weather Briefing |
00:08:00 |
Launch Pad Ordnance Armed |
T-4 Minutes |
Weather Update |
HOLDING |
Spacecraft to internal power |
HOLDING |
Final Status Polls |
HOLDING |
Launch Director GO/no GO; Range Clear |
00:04:00 |
Delta IV to internal Power |
00:04:00 |
Arm Safe and Arm Switches |
00:04:00 |
DCSS Tank Propellant Securing |
00:03:30 |
Transfer to Internal complete |
00:03:30 |
Common Booster Core Propellant Tank Securing |
00:03:15 |
CBC Pre-Press |
00:03:00 |
Common Booster Core LOX secure at Flight Level |
00:03:00 |
Common Booster Core LH2 secure at Flight Level |
00:03:00 |
Vehicle Ordnance Arming |
00:03:00 |
CBC LOX at Flight Level and Flight Pressure |
00:02:00 |
Master Script Running |
00:02:00 |
Second Stage LOX Securing |
00:02:00 |
Hydraulic System to Flight Pressure |
00:01:45 |
CBC LH2 at Flight Level and Flight Pressure |
00:01:30 |
Second Stage LOX secured at Flight Level |
00:01:20 |
Second Stage LH2 Securing |
00:01:20 |
LOX Ground Support Equipment secured |
00:01:00 |
Range Verification |
00:00:50 |
Second Stage LH2 secure at Flight Level |
00:00:45 |
Launch Enable |
00:00:45 |
Main Power Off |
00:00:25 |
Green Board |
00:00:15 |
Launch Vehicle Igniters armed |
00:00:14 |
Radially Outward Firing Initiators Ignition |
00:00:10 |
Terminal Countdown Sequencer in Control |
00:00:07 |
Starboard RS-68 Main LH2 Valve Open |
0:00:05.5 |
Center & Port RS-68 LH2 Valve Open |
0:00:03.5 |
Starboard RS-68 LOX Valve Open |
0:00:02.0 |
Center & Port RS-68 LOX Valve Open |
0:00:02.0 |
RS-68 Main Engines to Full Thrust Level – 102% |
0:00:00.04 |
Launch Commit |
0:00:00.00 |
Hold-Down Release |
0:00:00.00 |
LIFTOFF |